The main hall at Philadelphia’s William H. Gray III 30th Street Station looks more like a waiting room again. Amtrak and its partners reopened the station’s renovated South Concourse on Nov. 13 and finished restoring the 1930s hall, the first completed phase of a roughly $550 million overhaul scheduled to run through the end of 2028.
For anyone catching an Acela, Keystone, SEPTA regional rail or NJ Transit train there this holiday season, the change is mostly about where things are. Ticketing, information, baggage drop-off and Red Cap boarding help, which had been spread across the main hall for decades, now sit together in the north concourse, a smaller wing that had been rarely used, according to Skidmore, Owings & Merrill, the project’s architect. That move frees the hall itself for seating and for people walking through to the platforms.
What the restoration kept
The station is Amtrak’s third-busiest, and the building is on the National Register of Historic Places. SOM said the stone finishes, storefronts, bronze doors, Art Deco lighting and wood benches were restored under the Secretary of the Interior’s standards for rehabilitation, the federal rules for work on historic buildings.
Colin Koop, an SOM partner, said in Amtrak’s announcement that the first phase fulfills a goal of the 2016 master plan: “to create the heart of an equitable, transit-oriented district that bridges Center City and University City.”
Eating and waiting
The reopened South Concourse has new public restrooms and restored historic details, with a Dunkin’ and a Starbucks set to open soon. Amtrak said more food and retail spaces will open in phases over the coming months. SOM’s retail partner, Nelson Worldwide, laid out the concourse around a food hall with larger shop and restaurant spaces.
Behind the scenes, the work has also replaced much of the station’s machinery. Over the past two years, Amtrak said, new elevators and escalators were installed at four of the station’s five platforms, and the building now runs on new electrical substations and new heating and air-conditioning equipment.
What is still coming
With most of the south side done, major construction has moved to the north side of the nearly 500,000-square-foot station. Still ahead, according to Amtrak, are an upgraded Metropolitan Lounge, improvements to Market Street Plaza, better customer service and waiting areas, and more dining and shopping.
The upper floors are being converted too. Levels two through five are slated to hold more than 1,000 workstations for Amtrak staff, SOM said, consolidating employees in an operations hub inside the station.
The project is a public-private partnership between Amtrak and a team led by Plenary, with Vantage and Johnson Controls, and with Gilbane and SOM as the design-build team. Gilbane noted that the work is being done while trains keep running, so parts of the building remain construction zones.